Spa Valley Railway, West
Station, Royal Tunbridge Wells, Kent, TN2 5QY
Telephone: 01892 537715
Email: enquiriesatspavalleyrailway.co.uk
(Please replace 'at' with the @ symbol)
Eridge Extension News
There is a lot of work going into the extension to Eridge, both at the railway and behind the scenes with detailed negotiations between us and the other parties involved, namely Network Rail and Westinghouse Signalling Systems. Here is where you will find out detailed information regarding the extension and the work involved to return regular passenger services between Tunbridge Wells West and Eridge after a period of 23 years!!!
Latest
Eridge Extension News
BV Point Installation - Winter 2009
2008
Eridge News
2009 Eridge News
'Return to Eridge' Project Home Page
Eridge Project Requirements
Read
the Steam Railway Magazine Article "Great Eridge-pectations" outlining
the project
12th March - SIGNALLING UPDATE
Groombridge signalling continues to make good progress on two fronts with the onset of better (ahem) weather.
On the civils side, all the signal bases have now been cast and attention turned towards the retaining walls that are required around the two signal posts in Groombridge passing loop. In late February in what can only be described as a monsoon, the guys cast the final concrete base for the signals. This was around the former Down Birchden Junction distant signal, which is being converted into the Up Groombridge home signal. Having stood for all these years, it was felt that some extra support was required.

Above Left:- On 14th February the
shuttering is removed from around the signal base - Photo R. Sharpe
Above
Right:- On 7th March the retaining wall had reached half distance - Photo R.
Sharpe
Below:- The shuttering was then put in place ready for the next part
of the wall to be cast - Photo R. Sharpe

Below Left:- A view of the Up Home
signal base on Birchden Bank in mid February with all the formwork in place to
pour the concrete - Photo R. Sharpe
Below Right:- A couple of weeks later at
the beginning of March, the concrete had been cast and this element of the job
complete - Photo R. Sharpe

Elsewhere, the signal box has continued to make great strides since becoming weather tight. The locking room has benefited from some additional lighting whilst the leaver frame is rapidly being assembled. The latest work includes fitting the levers and tread plates. The building itself continues to receive coats of paint internally and the glazer has now commenced on fitting the individual panes of glass into the frames.

Above
Left:- A view of the signal box interior in early February showing the freshly
painted windows and associated woodwork - Photo R. Sharpe
Above Right:- At
the beginning of March the lever frame had been partially dismantled to allow
some refurbishment work - Photo S. Pay
Below Left:- By the 7th March the
tread plates had been refitted - Photo R. Sharpe
Below Right:- A few days
later on 10th March some of the levers and operating catches have been installed
into the frame - Photo R. Sharpe


Above Left:- A view from the locking
room shows where all the levers will be fixed to the frame - Photo R. Sharpe
Above
Right:- A view late on the 10th March shows all the levers fitted into the
frame. This is the first time since the mid 1980s when the frame was in Birchden
Junction signal box, that it has all be assembled - Photo R. Sharpe
ERIDGE
At Eridge our contractors, Gamble Rail, have moved in to complete another stage of works on the track in readiness for the commencement of operations. A groundframe has been transported from Tunbridge Wells West for use in controlling the crossover that enters the bay platform. At the same time Gamble Rail have removed the former crossover that led from the mainline into the long siding. This has been done because of the amount of work that would be required to keep the points in operational condition for the amount of use they would see. The points however have been removed and placed into store for eventual use elsewhere.

Above Left:- A view of some of the
new signalling rodding along with a ground signal in the bay platform at Eridge
in mid February - Photo M. Dives
Above Right:- A view towards London shows
just one crossover remaining in position. The other crossover started just after
the pointwork on the left and went back into the siding on the right. Some of
the new rodding can be seen on the far right - Photo M. Dives
5th February - SIGNALLING UPDATE
Since the beginning of the year, work has continued to progress on the signal box and signal post bases.
Fitting out of the signal box continues along with work commencing on the lever frame, which has recently been moved out of storage into the building itself.
January was spent making the framework up for the final signal base for this part of the signalling scheme. This base is located in the at the Tunbridge Wells end of the passing loop and will form the Up Starting signal for trains pulling into Groomrbridge platform. The foundation was dug out over a number of weeks in late 2009 and at the end of January the concrete base was poured. Once this has set and the framework removed, all that will remain to be done will be the retaining wall for both this base and the one at the far end of the loop for the Down Advanced Starting signal.

Above Left:- The framework for the
base under construction on 24th January - Photo R. Sharpe
Above Right:- On
31st January the concrete base has been cast, completing the project to cast all
the bases for the new signal posts. As can be seen, a retaining wall is yet to
be built at the back of the base - Photo R. Sharpe
This is possibly one of the most exciting times to get involved with volunteering at the railway. For more details on how to join the railway, click here.

Last Updated 12th March 2010. İM. Dives